SPD17B Topside & Ancillaries Installation
 
 
SPD 17B wellhead topside is 28m x 31m with base weight of 2,500 ton which is constructed in ISOICO yard and OMEGA KISH as installation MC subcontractor of LOICO ( www.loico.ir ) performed the Installation operation in South Pars Field- Persian Gulf.
 
For Heavy lifting operation HL5000 shear leg crane barge is chartered.
The topside is loaded out and rigged up in Bandar Abbas and sailed out on 2nd of December.
 
The Topside Installed on 24 of December 2016 and installation of related ancillaries including Bridge, Flare and flare tip completed on 27 of December 2016.
 
 

 
 

 
 
 