WPE-1, NASR-5 & WPE-3 platforms conductor installation
WPE-1, NASR-5 & WPE-3 belong to SIRRI oil field had been planned for developed by IOOC owner of the field, the project has been awarded by DCI contractor to omegakish offshore technology co.
WPE-1, 26 inch conductor installation was done on 26.Mar.2020. Pipes joint method was using belt tong, there were 10 joints for completion of the job. Total penetration of installed conductor pipes was 48m under seabed.
Performing PDA test was done as well.
NASR-5, 20 inch conductor installation was done on 27.May.2020. Pipes joint method was welding, total length of installed conductor pipes was 132m. Total penetration was 50m under seabed.
Performing PDA test was done as well.
WPE-3, 26 inch conductor installation was done on 29.Oct.2020. Pipes joint method was using belt tong, there were 10 joints for completion of the job. Total penetration of installed conductor pipes was 47m under seabed.
Performing PDA test was done as well.
Back
WPE-1, 26 inch conductor installation was done on 26.Mar.2020. Pipes joint method was using belt tong, there were 10 joints for completion of the job. Total penetration of installed conductor pipes was 48m under seabed.
Performing PDA test was done as well.
NASR-5, 20 inch conductor installation was done on 27.May.2020. Pipes joint method was welding, total length of installed conductor pipes was 132m. Total penetration was 50m under seabed.
Performing PDA test was done as well.
WPE-3, 26 inch conductor installation was done on 29.Oct.2020. Pipes joint method was using belt tong, there were 10 joints for completion of the job. Total penetration of installed conductor pipes was 47m under seabed.
Performing PDA test was done as well.