New Schedule for Installation of SPD17 Topside
2016-11-29 11:38:56
Based on weather forecast reports the new scheduel for Installation of SPD17B Topside , flare tower and also related link Bridge structure, are planned for second week of December 2016.

SPD 17B wellhead topside is 28m x 31m with base weight of 2,100 ton which is constructed in ISOICO yard and OMEGA KISH as installation MC subcontractor of LOICO is supposed to perform the Installation operation in South Pars Field- Persian Gulf.

For Heavy lifting operation HL5000 shear leg crane barge is chertered.
The topside is loaded out and rigged up in Bandar Abbas and will be sailed out on 2nd of December.